EPIC Midstream Completes Phase Two of NGL Pipeline
Construction continues on the third and final phase, from Benedum to Corpus Christi, and is expected to be complete in late 2019.
SEATTLE (Oil Monster): EPIC Midstream Holdings LP has completed the second phase of the EPIC NGL Pipeline that will carry natural gas liquids from the Permian Basin to Corpus Christi.
EPIC is now shipping product from DLK Black River Midstream through Reeves, Ward, Crane and Upton counties to Benedum, putting into service 205 miles of the total 700-mile pipeline. The San Antonio-based company had completed the first phase in March, a 40-mile segment from DLK Black River Midstream to Delaware Basin Midstream.
Construction continues on the third and final phase, from Benedum to Corpus Christi, and is expected to be complete in late 2019.
The pipeline is now connected to five processing complexes with a capacity of over a billion cubic feet.
In addition to announcing the completion of the second phase, EPIC said it has chosen Optimized Process Designs LLC of Houston to provide engineering, procurement and construction services for its first 100,000 barrel per day fractionation train at Robstown. The train is expected to be in service next year.
EPIC began construction of the NGL pipeline in December after reaching a definitive agreement with BP Energy Company to anchor the pipeline, which will ship NGLs from the Permian Basin and Eagle Ford to Gulf Coast refiners, petrochemical companies and export markets. The line will have a throughput capacity of over 400,000 barrels per day with multiple origin points in the Delaware and Midland basins.
The NGL line will run side-by-side with EPIC's crude oil pipeline, a 590,000 barrel-a-day pipeline from Orla to the Port of Corpus Christi. The crude line is expected to be in service next year.
Courtesy: www.mrt.com