ETP Appeals Revocation of Louisiana Pipeline Permit
The disputed pipeline is an extension to an existing line, which transports crude from Nederland, Texas, to Lake Charles, La.
SEATTLE (Oil Monster): An Energy Transfer Partners subsidiary on Feb. 26 appealed a ruling by a federal judge in Louisiana that halted construction on a portion of its Bayou Bridge crude oil pipeline, according to court documents.
The motion came after U.S. District Judge Shelly Dick on Feb. 23 issued a preliminary injunction revoking a needed permit for the pipeline, which is already under construction.
Environmental groups and local fisherman have opposed the line, citing concerns about the environment and local economy. A portion of the pipeline would run through the Atchafalaya Basin, a nearly 1 million-acre wetland in southern Louisiana that is a critical component of the state’s commercial fishing industry and flood protection system.
Representatives from Energy Transfer Partners did not respond to a request for comment. The project is 60% owned by ETP with the remainder controlled by refiner Phillips 66.
The disputed pipeline is an extension to an existing line, which transports crude from Nederland, Texas, to Lake Charles, La. The new segment would extend the system to St. James, Louisiana, and have capacity to transport up to 480,000 barrels per day (bbl/d) of oil.
Energy Transfer Partners last year prevailed over a fierce push from environmental and Native American groups to halt its controversial Dakota Access Pipeline. Although opponents of that line were able to temporarily stop construction, it began service in mid-2017.
The representative for the Association of Oil Pipe Lines, an industry group, on Feb. 17 noted the U.S. Army Corps of Engineers found that minimization, avoidance and mitigation efforts made during construction of the pipeline would result in “zero net loss of jurisdictional wetlands.” It also said the U.S. Fish and Wildlife service also said “the project is not likely to adversely affect any endangered species.”
Construction on the $750 million, 162-mile pipeline has already begun.
Courtesy: www.oilandgasinvestor.net
Track the prices behind the story
Daily prices for 281 crude grades, Brent–Dubai spreads, history back to 2009 and Excel downloads.