PUC Orders Emergency Shutdown of Key Natural Gas Pipeline
Mariner East 1 has been in operation since 2014, bringing propane and then ethane from the Marcellus and Utica gas fields through a processing plant in Houston, Washington County, to the Marcus Hook complex near Philadelphia.
SEATTLE (Oil Monster): The Pennsylvania Public Utility Commission late Wednesday ordered an emergency shutdown of the Mariner East 1 pipeline that runs from Washington County to the eastern part of the state.
The PUC said it wanted operations suspended on the Mariner East and an investigation with 24 hours due to concerns about structural integrity following reports of sinkholes in a township in Chester County near the construction of the Mariner East 2 pipeline, which recently was cleared for continued building after state action. Three sinkholes were found.
“The sinkholes are also near the area where construction, including Horizontal Directional Drilling (HDD), is underway for a new pipeline, known as Mariner East 2,” the PUC said.
The PUC’s order calls for inspections of the Mariner East 1 and other actions that PUC said in a news release would take about 10 to 14 days. The pipeline is owned by Sunoco Logistics, a division of Energy Transfer Partners, and is a key natural gas liquids link between southwestern Pennsylvania and domestic and international markets.
“During the Study Period, Sunoco shall maintain sufficient minimum pressure in Mariner East 1 to avoid gasification of NGLs. However, the NGLs shall not be flowing during such period,” according to the Public Utility Commission.
Energy Transfer Partners said it would inspect the pipeline and confirm its structural integrity plus investigate the geophysical and integrity in the area.
"This period should allow us to share what our professional geologist has established to date -- that the Mariner East 1 pipeline is stable, is located in suitably safe geology, and will continue to operate safely as it has done for decades. The safe operation of our pipelines is of critical importance to us, and we believe the study period will reaffirm the safety of the pipeline," the company said via email.
Mariner East 1 has been in operation since 2014, bringing propane and then ethane from the Marcellus and Utica gas fields through a processing plant in Houston, Washington County, to the Marcus Hook complex near Philadelphia.
Courtesy: www.bizjournals.com